Approx. Time: 2-4 Months* Approx. Fee: $3,400**
- Forms
Planning Permit Application Form - Regulations
Parking Regulations
If a project is unable to provide the required number of off-street parking spaces, the applicant can revise the project so that fewer spaces are needed. Another option is to apply for an Exception to Off-Street Parking Requirements.
Steps in the Planning Permit Process
If a planning or zoning permit is required, it generally needs to be processed prior to application of a building or construction permit. The Planning Section of the Planning and Building Department processes these permits. When multiple permits are required (e.g., Coastal Development Permit and Design Review Permit), the longer permit processing time and higher level decision-making body would apply to the concurrent processing of associated permits. In reviewing and processing your permit application, the assigned planner will generally complete the following steps:
1. Initial Application Review
The planner reviews your project to determine whether your application is complete. During this stage, the planner:
- Determines whether your project conforms with the County parking regulations to the extent feasible.
- Solicits comments and recommendations from review agencies (relative to their regulations) and applicable homeowners associations or community groups.
- Discusses your project with a development review committee of senior staff members.
The County has 30 days after receiving your application to notify you if you must provide any additional materials or information before your application can be processed.
2. Advisory Body Review
No advisory body review is required for projects outside of North Fair Oaks.
If the project is located in North Fair Oaks, a permit recommendation is made by the North Fair Oaks Community Council at their regularly scheduled meeting for projects involving:
- Residences with 3 or more bedrooms.
- Residences over 1,500 square feet.
- 2nd units.
- Major Remodels (project is over 50% of the valuation of the existing structure).
- Projects that received comments of objection by the public.
3. Public Notification
A public notice is mailed to owners of property within a 300-ft. radius of the subject property.
4. Permit Decision
A staff-level decision is required.
5. Appeal Period
Once a decision is made, both you and the public can appeal most permit decisions to a higher authority within 10 business days of the decision date. Staff-level decisions can be appealed to the Planning Commission. Planning Commission decisions can be appealed to the County Board of Supervisors. A decision by the Board of Supervisors is not appealable.
*
Approximated Time provides an estimated duration for processing of the specified permit only and does not include processing of any appeals. It is not intended to represent an exact timeframe for a specific project, which may be more or less than the time provided. Required permits and processing times vary depending on project complexity and location. For projects requiring multiple permits (e.g., Design Review Permit and Coastal Development Permit), please use the highest of the estimated times for each required permit. These times do not include processing times for non-Planning permits which may be required for the project, such as permits from the Building Inspection Section, Department of Public Works, Environmental Health Division, sewer or water districts, or state or federal agency. To obtain an estimated processing timeframe for a specific project, please call or visit the Current Planning Section and speak with a Planner to identify the required permits and reviews for your project.
**
Approximated Fees provide an estimated rounded fee total based on the permit fee and other anticipated review costs of the adopted Planning Service Fee Schedule and does not represent an exact fee amount for a specific project, which may be higher or lower than the fee provided. Required permits and fees vary depending on project complexity and location. For projects requiring multiple permits (e.g., Design Review Permit and Coastal Development Permit), please use the highest of the estimated permit fees and add on the established fees of other required permits from the Planning Service Fee Schedule, to obtain an estimated fee total. Other department review fees, including those of the Geotechnical Section, Department of Public Works, Environmental Health Division, and the applicable fire department, may also apply. To obtain an estimated fee total for a specific project, please call or visit the Current Planning Section and speak with a Planner to identify the required permits and reviews for your project.